Water Utility
Preliminary Utility Plan.

1. General. A Preliminary Utility Plan shall detail both 3.05.13: Water Utility and 3.05.14: Wastewater Utility requirements.

2. Illustrate the Location and Size of Water Utility and Wastewater Utility Mains.
a. Concurrent with the submission of a Preliminary Plat or Replat, the Developer shall submit a map or plan showing the location and size of Water Utility and Wastewater Utility mains, which will be required to provide adequate service and fire protection to the lots specified in the proposed plat.
b. Plans and specifications for fire hydrant systems shall be submitted to the City Engineer for review prior to construction.
 
3. Plan Document. The plan shall be prepared as noted in the City's Development Application Forms.

4. Coordination with other Utility Providers.
a. Preliminary Plat. When the subdivision is located in an area served by a utility provider other than the City, the Developer must provide a water system analysis, indicating adequate water supply and water quality.

b. Replat.
i. When a Subdivision is located in an area served by a utility provider other than the City, the Developer must provide a letter from the utility provider stating that facilities exist in the area to provide adequate domestic service and fire protection.
ii. If the City has reason to believe that there may be water supply or pressure concerns the City may require, a water system analysis, indicating adequate water supply and water quality.
 
c. Final Plat. The Final Plat will not be approved until a letter has been provided from the utility provider stating that they have accepted the plans for construction.